Road Resurfacing
Gilbert, Arizona


Description:

Milled and removed existing asphalt and resurfaced roadways for a total of 13.7 miles located at various locations in Gilbert, Arizona. Project included utility adjustments, re-striping, and installation of street light cameras.


Tangerine Road (various locations)
Arizona


Description:
We were the prime contractor on this ADOT project, responsible for pavement overlays with Asphaltic Concrete Asphalt Rubber (AR-AC), milling and replacing with Asphaltic Concrete (Miscellaneous Structural) and additional work includes pavement markings and other related work located at various locations in the Town of Oro Valley

US 60

Grand Avenue
Arizona

Description:

Being prime contractor for this Arizona Department of Transportation project (part of the economic stimulus program) we are responsible for 10 miles of road widening that involves integration of plan designs from 4 different civil designers. This project incorporates grading, paving, concrete, storm drain, street lighting, traffic signals, waterline, landscaping, irrigation, striping and signage.

Facts:

  • A stimulus project (ARRA)

SR 74 – New River Road
Arizona


Description:
As prime contractor on one of the first ARRA projects for the Arizona Department of Transportation our scope included the widening of a major highway (I-17), expansion of lanes on two bridges which involved a complex traffic control plan. An approach slab was poured, barrier walls were installed and retaining walls were built for the additional lanes. The contracted project schedule had a July 2010 completion which is ahead of schedule with an April finish, and had minimal public delays with no road closures.


Facts:

  • ADOT’s first “Stimulus” project (Arizona Recovery and Reinvestment Act)

US 93 & Hassayampa River Wickenburg, AZ


Description: Wickenburg Bypass, Wickenburg, AZ involved dewatering of groundwater with 28′ excavation for soil cement. In addition, borrow pits had water significantly higher than originally shown requiring a re-sequencing of the construction project to locate the aggregates within the project limits rather than external borrow sites stipulated in the project documents. This process was done while maintaining the master schedule. While drilling shafts 110 feet deep, two bridges built in the late 1800’s to early 1900’s were discovered. One was built out of wood piling which was used as a telegraph bridge. The other was built with rock and mortar and used for the usual form of travel in those days with horse and carriage. The Wickenburg Bypass is not only designed to detour traffic around Wickenburg, it also acts as a levy to take the town off the 50 year flood zone status and into the 100 year status.


Facts:

  • Prime Contractor for construction of 1.69 miles of new five lane roadway.
  • Replacement of a bridge and raising of another over the Hassayampa River.
  • Constructed a new bridge over Sols Wash.

Happy Valley Road at I-17
Phoenix, AZ


Description:
This project was the first round-a-bout constructed in the state. It crossed over I-17 on Happy Valley Road. The project was built as a temporary way to move cars coming and going to and from a major corporate park onto the freeway. This project created a lot of controversy on its ease of use. People either really like it or they really don’t.


Facts:
First round-a-bout on a major arterial road in Arizona.