El Mirage

Surprise,
Arizona

Description:

We are the prime contractor of this project located along El Mirage Road beginning at the intersection of Bell Road running north 3.78 miles to Deer Valley Access Road. Consisting of new asphalt pavement, roadway widening along Bell Road, El Mirage Road, Deer Valley Road, extension of the existing multiple cell box culvert at the north side of the Bell Road intersection, construction of two new culverts for McMicken Wash, and traffic signal work.

 

 

 

Prescott Valley
Arizona

Description:

We were prime contractor for this Prescott Valley project that involved building the first phase of a 10 mile, concrete multi use path for the Town of Prescott Valley to connect the town’s landmarks. This phase connects the middle school and high school with the town hall and town library. It included the installation of a pedestrian bridge that crosses over a channel to where future commercial sites are designated to be. The American Recovery and Reinvestment Act helped pay for this segment of the pathway.

Facts:

  • Extreme weather conditions made this project challenging but it didn’t stop us, we forged ahead and still were able to complete this project within the contracted time frame.

 

Surprise,
Arizona

Description:

We were the prime contractor for the road widening and improvements on Bullard Avenue between Bell Road and Paradise Lane in Surprise, AZ. This project included the installation of a landscaped median, the extension of a reclaimed waterline, and modification of the traffic signal.

Facts:

  • Bullard Avenue is the entrance to Surprise Stadium…the Spring Training Home of the Texas Rangers and Kansas City Royals.

 

Goodyear, AZ

Description:

1 mile – 6 lane street. Mill and overlay with rubberized asphalt. 2 new left turn lanes. Traffic remained open in both directions during construction.

Facts:

  • McDowell Road between Bullard & Pebble Creek Parkway.

 

Golden Eagle Blvd & Palisades
Fountain Hills, AZ

Description:

We were the General Contractor for construction of this 25 acre community park. The park included baseball fields, ramadas, dugouts, soccer fields, lighting and landscaping. As this park was developed around an existing residential area, we were actively involved in assuring that the needs and questions of the local residents were addressed in a timely manner.

Facts:

  • Twenty-Five acre recreation area adjacent to the middle school/high school.

 

 

Various Streets Improvements
Fountain Hills, AZ

Description:

We performed maintenance for the Town of Fountain Hills for 6 consecutive years involving sidewalk removal and replacement, asphalt paving, curb and gutter, excavation and storm drainage. Projects were normally on tight schedules, and we would perform the maintenance projects within or ahead of the original schedule.

Facts:

  • Situated on the eastern slope of the McDowell Mountains about 500 feet in elevation above Phoenix.
  • Population in 2009 is approximately 25,500 people with an estimated population of 34,324 in 2030.

Estrella Pkwy & Wood Blvd
Goodyear, AZ

Description:

The Cincinnati Reds Spring Training Complex required precise contouring of full size baseball fields and two half size fields. By using our GPS equipment controls in conjunction with the engineering CAD files we were able to reduce the general contractor’s survey costs while maintaining high levels of accuracy. Due to the critical time constraints on the project it was important that we coordinated construction of the parking lot to allow continued clubhouse construction, coordinated deliveries and provided unobstructed access for other trades at all times.

Facts:

The Spring Training Ballpark Complex was completed February 2009.
The ballpark is located on a 3 acre parcel.
The Cleveland Indians will be joined by the Cincinnati Reds in 2010.
Each team gets 2 practice fields for their own use year round, while the other eight are for residential use in months when spring training is not active.

9301 W. Maryland
Glendale, AZ


Description:
Construction of the Cardinal’s Stadium started with an extremely tight schedule that many earthmoving and paving contractors told the general contractor “couldn’t be done “. We took the challenge of the expedited schedule and moved 190,000 cy of dirt, placed 71,700 tons of asphalt and 159,000 tons of ABC. Working multiple shifts 7 days a week, we finished our scope of construction and turned the project over early to the general contractor, exceeding their expectations.


Facts:

  • Home of the Arizona Cardinal’s.
  • Groundbreaking was held on April 12, 2003.
  • Unique design with a retractable roof and roll out field to accommodate many types of events.

Bell Road – Grand Avenue to Loop 303
Surprise, AZ


Description:
These improvements were awarded in multiple phases of construction consisting of several miles along Bell Road west of Grand Avenue to Loop 303. Markham was prime contractor self performing 90% of the work. We provided alternative traffic control ideas to minimize business traffic interruptions and completed 50% ahead of schedule. Coordination with the Railroad, ADOT, and City of Surprise was key to our early completion.


Facts:

  • Multi phase construction.
  • Main thoroughfare into West Valley.