Description:

The Cincinnati Reds Spring Training Complex required precise contouring of full size baseball fields and two half size fields. By using our GPS equipment controls in conjunction with the engineering CAD files we were able to reduce the general contractor’s survey costs while maintaining high levels of accuracy. Due to the critical time constraints on the project it was important that we coordinated construction of the parking lot to allow continued clubhouse construction, coordinated deliveries and provided unobstructed access for other trades at all times.

Facts:

The Spring Training Ballpark Complex was completed February 2009.
The ballpark is located on a 3 acre parcel.
The Cleveland Indians will be joined by the Cincinnati Reds in 2010.
Each team gets 2 practice fields for their own use year round, while the other eight are for residential use in months when spring training is not active.